Avg . Generation on
Tuesday, August 19, 2014
1412.0763 M.W.
Power Station
Avg. Gen. (MW) on Tuesday, August 19, 2014
Burla
118.8330 
Chiplima
45.4170 
Balimela
274.8063 
Rengali
235.0250 
Upperkolab
98.6200 
Indravati
600.0000 
Machhkund
(Odisha drawl)
39.3750 
Total
1,412.0763 
Zone Tender No Sale Open Sale Close Last Date (Receive)
Tender Open
UIHEP, Mukhiguda UIHEPM-21-2014-15 Thursday, August 21, 2014 Friday, September 05, 2014 Wednesday, September 10, 2014
12:30 Hrs
Wednesday, September 10, 2014
12.30 Hrs
Metal Spreading at 400KV Switchyard at UIHEP, Mukhiguda.(e-Procurement Notice) Notice Download
[  Notice Download  ]
UIHEP, Mukhiguda UIHEPM-20-2014-15 Thursday, August 21, 2014 Saturday, September 06, 2014 Saturday, September 06, 2014
11.00 Hrs
Saturday, September 06, 2014
12.30 Hrs
Cleaning of drains Shrub jungles and uprooting stumps and small bushes trees below 1m girth around the Central Store area and Power house Garden area for One year. Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
UIHEP, Mukhiguda UIHEPM-18-2014-15 Wednesday, August 20, 2014 Wednesday, September 03, 2014 Friday, September 05, 2014
11:30 Hrs
Friday, September 05, 2014
11:30 Hrs
Repair and Maintenance of Power House Colony roads at Sector I, Mukhiguda for the year 2014-15.(e-Procurement Notice) Notice Download
[  Notice Download  ]
UIHEP, Mukhiguda UIHEPM-19-2014-15 Monday, August 18, 2014 Thursday, August 28, 2014 Thursday, August 28, 2014
11.00 Hrs
Thursday, August 28, 2014
12.30 Hrs
Construction of Concrete plat form for parking of Vehicles in front of EQ-2 and EQ-3 at UIHEP, OHPC Ltd., Mukhiguda. Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
UIHEP, Mukhiguda UIHEPM-17-2014-15 Saturday, August 16, 2014 Tuesday, August 26, 2014 Tuesday, August 26, 2014
11.00 Hrs
Tuesday, August 26, 2014
12.30 Hrs
Supply & Fixing of M.S. Grills for EQ & CR Type quarters at Power House Colony, UIHEP, Mukhiguda. Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
BHEP, Balimela BHEP-5198-2014 Friday, August 15, 2014 Monday, August 25, 2014 Tuesday, August 26, 2014
04:00 PM
Tuesday, August 26, 2014
04:30 PM
Overhauling,repairing & Re-insulation/rewinding of old & used copper wound distribution transformer of diffrent ratings,BHEP,Balimela. Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
UIHEP, Mukhiguda UIHEPM-14-2014-15 Thursday, August 14, 2014 Thursday, August 28, 2014 Tuesday, September 02, 2014
11:30 Hrs
Tuesday, September 02, 2014
11:30 Hrs
Construction of RCC building for fuse call section, Utility Sub-Division No.- III.(e-Procurement Notice) Notice Download
[  Notice Download  ]
UIHEP, Mukhiguda UIHEPM-13-2014-15 Thursday, August 14, 2014 Monday, August 25, 2014 Monday, August 25, 2014
11.00 Hrs
Monday, August 25, 2014
12.30 Hrs
Procurement of Electrical Materials (Cables). Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
UIHEP, Mukhiguda UIHEP-15-2014-15 Tuesday, August 12, 2014 Tuesday, August 26, 2014 Monday, September 01, 2014
11:30 Hrs
Monday, September 01, 2014
11:30 Hrs.
Raising and Painting of Switchyard boundary and improvement of Central Store Boundary.(e-Procurement Notice) Notice Download
[  Notice Download  ]
BHEP, Balimela BHEP-5092-2014 Monday, August 11, 2014 Thursday, August 28, 2014 Thursday, August 28, 2014
04:00 PM
Thursday, August 28, 2014
04:30 PM
Replacement of 15 Nos Old 220KV CTs with new Top Core 220KV CT inside Switch Yard of BHEP, Balimela. Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
BHEP, Balimela BHEP-5079-2014 Monday, August 11, 2014 Wednesday, August 20, 2014 Thursday, August 21, 2014
12.00 Noon
Thursday, August 21, 2014
12.30 PM
Annual running maintenance of civil works and annual sewerage cleaning of Kalichawk, Pump House Colony, Electrical Section office and Building Section Office, BHEP, Balimela. Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
CHEP, Chiplima CHEP-18-2014-15(SlNo.1 & 2) Friday, August 08, 2014 Monday, August 18, 2014 Monday, August 18, 2014
11.30 AM
Monday, August 18, 2014
12.00 Noon
STANDARD FIRE AND SPECIAL PERIL INSURANCE POLICY OF PLANT, MACHINERIES, EQUIPMENTS & BURGLARY INSURANCE POLICY OF STORES UNDER CHEP. Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
UKHEP, Bariniput UKHEP-09-2014-15(Group-B) Wednesday, August 06, 2014 Wednesday, August 20, 2014 Wednesday, August 20, 2014
16.00 Hrs
Friday, August 22, 2014
16.00 Hrs
Periodic, routine and emergency Maintenance of control & relay panels in MCR, S/Y. UCP, Static excitation system Panels, G.T, UAT, S.S.T, all associated switchgears, illumination system & such other Elect maintenance works on job contract basis. Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
UKHEP, Bariniput UKHEP-09-2014-15(Group-A) Wednesday, August 06, 2014 Wednesday, August 20, 2014 Wednesday, August 20, 2014
16.00 Hrs
Friday, August 22, 2014
16.00 Hrs
Periodic, routine and emergency maintenance of 4 x 80 MW Hydro Generating unit and other equipments with their auxiliaries on job contract basis. This is to support core group of OHPC workmen. Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
CHEP, Chiplima CHEP-21-2014-15 Monday, August 04, 2014 Monday, August 18, 2014 Monday, August 18, 2014
01:00 PM
Monday, August 18, 2014
03:30 PM
Repair & overhauling of Head Regulator Gates of Power Channel of CHEP, Chiplima. Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
UKHEP, Bariniput UKHEP-08-2014-15 Monday, August 04, 2014 Wednesday, August 20, 2014 Wednesday, August 20, 2014
16.00 Hrs
Friday, August 22, 2014
16.00 Hrs
Periodic, routine and emergency Maintenance of 11 KV lines from UKPH Switchyard to Bariniput& PH Colony etc. Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
UKHEP, Bariniput UKHEP-07-2014-15 Wednesday, July 30, 2014 Monday, August 18, 2014 Monday, August 18, 2014
16.00 Hrs
Thursday, August 21, 2014
16.00 Hrs
Supply of 48 Nos Thordon SXL Elastomeric Bushes (As per drawing). Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
RHEP, Rengali RHEP-01-2014-15 Monday, July 28, 2014 Thursday, August 14, 2014 Thursday, August 14, 2014
04:30 PM
Monday, August 18, 2014
04:00 PM
Annual maintenance and operation of 33 KV line, 33/11 KV Sub-station switchyard, 11 KV line, 11/.4KV distribution Transformers with Sub-stations, LT lines, Street lights, Service connections and internal wiring works of O.H.P.C staff quarters. Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
UKHEP, Bariniput UKHEP-06-2014-15 Thursday, July 24, 2014 Thursday, September 04, 2014 Thursday, September 04, 2014
16.00 Hrs
Saturday, September 06, 2014
16.00 Hrs
Deployment of Diesel Run Commercial Registered Light Vehicles at UKHEP, Bariniput.(Group A,B,C & D)
Corrigendum Download
[  Corrigendum Download  ]
Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
Corporate Office, Bhubaneswar OHPC-CNP-12-2014-15 Thursday, July 24, 2014 Tuesday, August 05, 2014 Tuesday, August 05, 2014
01:00 PM
Tuesday, August 05, 2014
03:30 PM
Procurement of Office Stationeries for the year 2014-15 for OHPC Corporate Office, Bhubaneswar. Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
BHEP, Balimela BHEP-4657-2014 Monday, July 21, 2014 Tuesday, August 05, 2014 Tuesday, August 05, 2014
01:00 PM
Tuesday, August 05, 2014
04:00 PM
Rebabbiting of Thrust Bearing Pads for 60 MW Hydro Generator. (Make Electrosila USSR.) Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
BHEP, Balimela BHEP-4619-2014 Monday, July 21, 2014 Tuesday, August 05, 2014 Tuesday, August 05, 2014
01:00 PM
Tuesday, August 05, 2014
04:00 PM
Engagement of 14 nos. ITI personnel for operational work of 6x60 MW & 2x75 MW Hydro Generator of B.H.E.P, Balimela. Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
RHEP, Rengali RHEP-03-2014-15(Grp-B) Tuesday, July 22, 2014 Tuesday, August 05, 2014 Tuesday, August 05, 2014
04:30 PM
Thursday, August 07, 2014
04:30 PM
Replacement of conductors by using XLPE insulated 55 mm2 AAA conductor for 3 phase, five wire, LT line of length 06 (six) KM of electrical colony under RHEP, Rengali. Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
RHEP, Rengali RHEP-03-2014-15(Grp-A) Tuesday, July 22, 2014 Tuesday, August 05, 2014 Tuesday, August 05, 2014
04:30 PM
Thursday, August 07, 2014
04:00 PM
Replacement of Conductors by using 55 mm2 AAA conductor for 11 KV, 3 Phase line of Electrical Colony & Hatiadanda Colony of 3.5 Kms. Length under RHEP, Rengali. Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
UKHEP, Bariniput UKHEP-05-2014-155 Thursday, July 17, 2014 Tuesday, August 05, 2014 Tuesday, August 05, 2014
16.00 Hrs
Friday, August 08, 2014
16.00 Hrs
Supply of 02 Nos. of Tube Bundles each for 550KW and 500KW Oil draught water forced Transformer Cooler for 102MVA,11KV/230V Generator Transformers of UKHEP,Bariniput. Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
HHEP, Burla HHEP-68-2014 Tuesday, July 15, 2014 Monday, August 25, 2014 Tuesday, August 26, 2014
03.30 PM
Tuesday, August 26, 2014
04:00 PM
Repairing of Thrust Bearing Oil Cooler of Unit no. 7.
Corrigendum Download
[  Corrigendum Download  ]
Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
UKHEP, Bariniput UKHEP-04-2014-15 Tuesday, July 15, 2014 Monday, August 18, 2014 Monday, August 18, 2014
16.00 Hrs
Wednesday, August 20, 2014
16.00 Hrs
Supply, Erection, Testing & Commissioning of 4 Nos. of 245 KV, 3 phase, 3150 A, 50 Hz, SF6 Circuit Breakers.
Corrigendum Download
[  Corrigendum Download  ]
Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
RHEP, Rengali RHEP-04-2014-15 Monday, July 14, 2014 Thursday, August 21, 2014 Thursday, August 21, 2014
04:30 PM
Saturday, August 23, 2014
04:00 PM
Annual Sewerage & sanitary cleaning of Rengali Power House, General Store, Residential and Non- Residential buildings under RHEP.
Corrigendum Download
[  Corrigendum Download  ]
Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
CHEP, Chiplima CHEP-10-2014-15(Sl.No.1) Friday, June 20, 2014 Monday, August 25, 2014 Monday, August 25, 2014
01:30 PM
Monday, August 25, 2014
03:30 PM
2nd Corrigendum to Supply of EHV Grade Transformer Oil.
Corrigendum Download
[  Corrigendum Download  ]
Document Download
[  Document Download  ]
Notice Download
[  Notice Download  ]
Corporate Office, Bhubaneswar OHPC-R&M-03-2014 Thursday, March 06, 2014 Saturday, April 05, 2014 Tuesday, August 26, 2014
01:00 PM (IST)
Tuesday, August 26, 2014
03:00 PM(IST)
CORRIGENDUM-Design,Manufacture,Supply,Erection,Testing and Commissioning os 2 sets of New Turbine & Generator in Unit 5&6 (2X43.6 MW) with auxiliaries of HHEP,Burla,Odisha,India.
Corrigendum Download
[  Corrigendum Download  ]
Notice Download
[  Notice Download  ]
Corporate Office, Bhubaneswar OHPC-R&M-02-2014 Tuesday, March 04, 2014 Saturday, April 05, 2014 Monday, August 25, 2014
01:00 PM (IST)
Monday, August 25, 2014
03:00 PM (IST)
CORRIGENDUM 2-Renovation & Modernisation with new Turbine-Generator Power Generating Unit-1 to 6(1X60MW) of Balimela Power House at Balimela, Malkangiri, Odisha, India.
Corrigendum Download
[  Corrigendum Download  ]
Notice Download
[  Notice Download  ]
Corporate Office, Bhubaneswar OHPC-R&M-01-2014 Monday, March 03, 2014 Saturday, April 05, 2014 Tuesday, August 05, 2014
01:00 PM (IST)
Tuesday, August 05, 2014
03:00 PM (IST)
CORRIGENDUM-Renovation & Modernisation with new Turbine-Generator Power Generating Unit-3 (1X24 MW) of Chiplima Power House at Chiplima,Odisha, India.
Corrigendum Download
[  Corrigendum Download  ]
Notice Download
[  Notice Download  ]